Development of Tawi River Front (TRF) and Real Estate Development
Development of Tawi River Front (TRF) and Real Estate Development
• Project Cost: ₹ 179.26 Cr .
• Date of Start : 20-Feb-2022
• Date of Completion as per Contract: Aug’23
• Expected Completion Date – November’ 23
• Financial Progress: ₹ 61.60 Cr( Left Bank: ₹ 32.51 Cr and Right Bank : ₹ 29.69 Cr)
• Physical Progress: 56% (Left Bank) and 54%(Right Bank) , Overall – 55%(Left + Right Bank)
TRF: Land Monetisation Strategy: Reclaimed Land & adjoining areas
TRF: Land Monetisation Strategy: Reclaimed Land & adjoining areas
- Name of the Consultant : M/S CBRE South Asia Pvt. Ltd.
- Duration of Consultancy : 5 years w.e.f. Dec.’2022 to Dec.’2027
- Consultancy Fee: ₹6.27 Cr. (excluding G.S.T.)
- Scope of Work:
- Activity 1 – Report suggesting the best land use matrix and revised DCR along with Architectural drawings which shall fetch the maximum return on investment for JSCL (for reclaimed land and adjoining areas).
- Activity 2 – Strategic and Financial Business Plan for Land Monetisation of reclaimed land and adjoining areas(warehouse).
- Activity 3 – Marketing, Branding and Positioning Strategy (for reclaimed land and Central Island only).
- Activity 4 – Transaction Advisory (for reclaimed land and Central Island only).
- Areas: Reclaimed land
- Left Bank – 90,000 Sqm (22.24 Acres)
- Right Bank – 41,505 Sqm (10.26 Acres)
- Central Island – 1,33,470.71 Sqm (32.98 Acres)
- Adjoining Areas – Warehouse – 2,76,653 Sqm (68.36 Acres)
- Total Area – 133.84 Acres
Blue Green: Ranbir Canal-I from BSF Paloura to Shakti Nagar Bridge
Blue Green: Ranbir Canal-I from BSF Paloura to Shakti Nagar Bridge
- Project Cost: ₹ 15.03 Cr.
- Physical Progress (Blue Green - 1): 49%,Financial Progress : ₹ 5.35 Cr.
- Edge wall roadside - 1200Mt. and edge wall canal side - 1350 Mt.
- Slab casted - 2 nos. toilet blocks , Softscape work is in progress
- Footpath work from toph bridge towards Eden garden – in progress on left bank of canal, Pole foundation work - in progress, Civil work for planters/Tree guards in progress, Fixing of Benches – 32 No completed
- Fixing of kerb stone in progress, Fixing of red sandstone on walkway and walls - in progress.
- Fabrication and installation of MS railing Completed, Drain work on Left hand side of canal - completed.
Execution Period: 18 Months.Timeline: Tentative Completion by 20-11-2023
Project Features :
- Improved access to the park / Pergola's seatings/ Paved courts in park area/Lower deck areas.
- Landscape lawns.
- 2.80-Metre-wide sandstone path for morning walkers.
- Seating benches and Parking for vehicles and Decorative lighting along the walkway and Footpath works on left hand side of canal.
Blue Green: Tawi Canal from Gorkha Nagar to Railway Station
Blue Green: Tawi Canal from Gorkha Nagar to Railway Station
- Project Cost: ₹ 18.83 Cr.
- Project Status: Work in Progress.
- Physical Progress : 82%, Financial Progress : ₹ 8.50 Cr
- Date of Start: March 2022
- Likely Completion Date : 30-09-2023
Project Features:
- Construction of walkways with paver tiles on both sides of canal.
- Canal of RCC parapet with red sandstone cladding and railing on both sides of Tawi Canal.
- Development of Green spaces and plantation work along canal at various locations.
- Construction of double storied parking for 29 Vehicles.
- Decorative street lighting on both sides of canal.
- Construction of Public toilets and Renovation of Park at Gorkha Nagar.
- Renovation of damaged canal lining by RTIC Department.
- Pedestrian bridges to connect left and right side of Canal bank.
- Construction of drains in habitations along canal and Providing of Public amenities like Water ATM’s ,Dustbins and benches etc.
City Landscaping and Beautification
City Landscaping and Beautification
- Project Cost: ₹ 38.60 Cr.
- Physical Progress : 45%.
- Date of Start : February – 22
- Date of Completion : December-2023
Project Features :
- Landscaping and Beautification by INTACH
- Wall Paintings and 3D Murals – Work at different locations in progress.
- Landscaping of Road outside Jammu University, Maha Maya Temple complex and upgradation of Approach road to Maha Maya Temple
- Beautification of Divider of Flyover from Bikram Chowk to Gandhi Nagar, Jammu: Completed.
- Remodeling of triangular divider around Maharaja Hari Singh Statue near Tawi Bridge, Jammu 41m high pole for raising Indian Flag
- Aesthetics of Bahu Fort Park, common façade including new Entrance of Bahu Fort Market, old parking area and Road -side Features near Bahu fort Jammu.
- Establishment of Nakshtra Vatika ,Navgraha Van ,Rashi Van, and Memory Forest and Illumination of Poles from Airport to Raj Bhawan.
Oceanarium at Bagh-e- Bahu
Oceanarium at Bagh-e-Bahu
- Project Cost: ₹ 19.03 Cr.
- Project Status: Work in progress
Project Features :
- Development of Sea walk- or Walk-through Tunnel Aquaria.
- Utilizing the existing unused space to create a massive underground Tunnel to get 360 Degree vision of Sea water fishes.
- It will also help visitors to learn and understand the biology, physiology, behavior of fish and ecosystem interactions and components.
- Development of Marine Interpretation center.
- Use of 3D technology for Education purposes for the visitors
Project Outcomes:
- Creation of a vibrant social space for tourism.
- Educating and imparting knowledge to the visitors about underwater world.
- With increase in footfall of tourists, will create more employment opportunities to the locals.
Supply, Operation & Maintenance of 100 eBuses on GCC with NCMC Compliant Digital Tickets Solutions in Jammu City
Supply, Operation & Maintenance of 100 eBuses on GCC with
NCMC Compliant Digital Tickets Solutions in Jammu City
- Name of Executing Agency – Jammu Smart City Limited.
- Project Cost : ₹ 500.00 Cr. (Approx)
- Opex VGF from H&UDD, Govt. of UT of J&KCapex
- MHI Subsidy under FAME-II for CAPEX: ₹47.00 Cr
- Contract Date: 17th October 2022
- Duration of Project – 12 Years
- Service Provider:
- TATA Motors Ltd. (eBus)
- Chalo Mobility (NCMC Digital Tickets)
Apsara Road "High Street" Gole Market along with Adjoining Roads
• Project Cost: ₹ 51.53 Cr.
• Awarded Cost : ₹ 46.22 Cr. ( Excluding utility shifting)
• Physical Progress for Civil works : 67% Construction of CC roads ,BC Road, Cobble stone pavement at Apsara Road, footpaths , Drains , Façade work of Apsara Road gate, underground utility duct & drains
• Financial Progress : ₹ 23.00 Cr.
• Date of Start : 07-02-2022, Likely Completion Date : 30-09-2023.Project Features
• Cobble stone carriage way at Apsara road / Tabletop crossings
• Construction of undergound Drain & utility Duct for PDD and BSNL HT/LT & communication cables.
• Pedestrian friendly footpaths along roads and Renovation /upgradation of Gate
• Parking bays along roads.
• Road improvement works in Gandhi Nagar Area, Length – 13.64 Km.
• Decorative Street lighting /New water points.
• Road signages and caution boards.
• Benches and dustbins and Up-gradation & Landscaping of Gole market park
• Undergrounding of public utilities at Apsara Road including compact sub stations.
Smart Equipment for Solid waste management
- Project Cost: ₹ 5.34
- Executive Agency : Jammu Municipal Corporation.
Project Features:
- Procurement of crawler hydraulic excavator
- Procurement of truck mounted water tanker with sprinkler of capacity 6000 litre.
- Procurement of small jetting cum Suction machine of 1000 litre capacity.
- Procurement of 05 No. Tractor towed 10-seater mobile Toilets.
- Procurement of 05 No. Tractor towed 04-seater mobile toilets.
- Procurement of 03 No. Tractor along with mechanized open drain cleaning machine.
- Procurement of 03 No. truck mounted water tanker having capacity 3000 litre.
- Procurement of 03 No. truck mounted water tanker having capacity 9000 litre.
- Procurement of 05 Nos. Tractor towed stainless steel portable water tanks on two-wheel Trailor of capacity 3000 litre.
- Procurement of 05 Nos. Tractor towed stainless steel portable water tanks on two-wheel Trailor of capacity 5000 litre.
E- Bicycle under Public Bicycle Sharing System
Flag off to E- Bicycle under Public Bicycle Sharing System.
- Project Cost: ₹ 7.56 (₹4.57 Cr. VGF)
- Executive Agency : Jammu Municipal Corporation.
- Execution Period: 6 months and 5 years O&M
- Project Status: Total Station Installed: 100,Total Bicycle deployed: 687,
- E - bicycles - 100 No. ready for launching.
Project Features :
- 800 bicycles with nearly 120 docking stations (each covering 8-12 Bicycle stands) in Jammu city
- App-based GPS enabled locking and tracking system
- Check-out from any stand – Check-in at any stand.
- One click registration
- Sturdy bicycles with front basket and 7-year lifecycle
- 80 no. Pedal assist Electrical Bikes + 720 Unisex Bicycles
Facade illumination of 11 statues at Junctions
Landscaping and Beautification near Balidan Stambh
Landscaping and Beautification near Balidan Stambh.
- Project Cost: ₹ 1.07 Cr.
- Executing Agency : JSCL.
Project Status:
- Physical Progress Work Completed
Project Features
- Construction of footpath.
- Construction of paved area with red sand stone.
- Construction of Saucer and inner drain.
- Installation of 09 planters.
- Development of green spaces.
- Development of pathway
- Installation of Sculpture.
- Installation of SS railing.
- Installation of poles.
- Installation of spikes and bollard light.
- Provision of Benches and dustbins and Installation of Chain fencing at backside wall.
Landscaping of Road Outside Government College for Women (From Presentation Convent School Gate Up to Asia Hotel).
Landscaping of Road Outside Government College for Women (From Presentation Convent School Gate Up to Asia Hotel).
- Project Cost: ₹ 0.45 Cr.
- Executing Agency : JSCL.
Project Status:
- Physical Progress Work Completed
Project Features:
- Construction of Footpath from Govt. college for women to Asia.
- Construction of Saucer Drain and Grass Pavers.
- Provision of R.C.C Seating with Granite.
- Provision of Granite on Platform for Selfie Wall.
- Planter Work.
- Construction of SS Sculpture 304 Grade (2.7 x1.1m, cnc cut 3mm thick Wing Shaped with SS Frame R.H.S 120x 80 x 3mm of Size 2.7x2.1 m).
- Development of Green spaces by planting different kind of Trees like Bauhinia blakeana, Cassia Fistula, Cycas Revoluta.
- Development of Green spaces by planting different kind of climber like Clerodendrum Splendens, Quisqualis Indica.
- Development of Green spaces by planting different kind of shrubs like Fiscus Panda, Taberna Monta coronaria Dwarf, Hamelia Patens Dwarf, Tecoma Purpurea Splendens.
Landscaping and development of green spaces in road outside Jammu University from Hostel Gate up to J&K Bank
Landscaping and development of green spaces in road outside Jammu University from Hostel Gate up to J&K Bank
• Project Cost: ₹ 1.45 Cr.
• Executing Agency : JSCL. Project Status:
• Physical Progress Work CompletedProject Features
• Construction of Drain.
• Construction of footpath.
• Development of Selfie Point.
• Construction of Fountain.
• Fabrication of MS pergolas.
• Provision of Dustbins, benches.
• Development of Green Spaces.
• Installation of Sculptures.
Cycle Track at different Locations
Cycle Track at different Locations
- Project Cost: ₹ 2.07 Cr.
- Executing Agency : JSCL.
- Physical Progress : Work completed for 04No. cycle tracks
Project Outcomes :
- Development of Cycle tracks for providing facilities to various age groups of people from children to elder.
- Providing of dedicated tracks for cycling with secured accident-free facility.
- Improving the general health of the people.
- Reducing the pressure on traffic.
Smart Traffic Police Booths
Smart Traffic Police Booths
Project Cost: ₹ 0.65 Cr.
Project Features of Smart Police Booths
- Smart Traffic Booths at 25 Locations identified by Traffic Police in Jammu City
- The traffic booths will be pre-fabricated using 50 mm thick PUF panelling walls & Pre-fabricated Single unit Toilets.
- Single unit prefabricated Toilets at 15 No. locations of Traffic Booths.
Project Outcomes:
- For providing facilities to the traffic police by way of safe accommodation along with furniture at junctions
- Secured shelters with electric fans for comfort of Traffic police.
- Improvement in efficiency for discharging the duty by way of this amenity including Toilet facility .
Development of Indoor Gym and Park at Channi Himmat
Development of Indoor Gym and Park at Channi Himmat
- Project Cost : ₹ 3.71 Cr.
- Name of Executing Agency : JMC
- Physical Progress at Indoor gym : 100%
- Financial Progress Indoor gym : ₹ 2.05 cr.
Project Features of Indoor Gym and Park at Channi Himmat:
- Construction of Indoor Gym.
- Development of Community hall.
- Development of Park.
- Development of children play area.
- Health and Fitness equipment's.
- Street Lighting in the park area.
Project Outcomes:
- A State the Art gym along with adjacent park is being developed at Channi Himmat for inculcating importance of good health and cultivating of good habits.
- A vocational centre along with adjoining park is also being developed with above mentioned purpose.
Modernization of Narwal Fruit / Vegetable Mandi
Modernization of Narwal Fruit / Vegetable Mandi
- Project Cost: ₹ 9.56 Cr.
- Project Award Cost : ₹ 9.235 Cr.
- Date of Start : 06-07-2021, Date of Completion- 28-02-2023
- Name of Executing Agency : PWD
- Physical Progress: 100%
- Financial Progress : ₹ 9.56 Cr.
Project Features :
- Up-gradation and improvement of existing sheds
- Construction of Canteen, Mandi Plaza Building(G+2),
- Toilet block , Compound wall, footpaths and Kiosk
- Adequate parking facility and weigh Bridge- 100 MT
- Safe drinking water facility, Water ATM’s.
- Proper drainage, garbage composters plants.
- Beautification of existing park
Repository at Kala Kendra
- Project Cost : ₹ 7.71 Cr.
- Date of Start : August – 2022
- Date of Completion : November 2023
- Physical Progress : 80% , Financial Progress : ₹ 5.80 Cr
Project Features
- Provide a proper environment for the purpose of storing records and materials that require permanent protection for historic and lifetime storage, upkeep, and preservation.
- Archives Friendly Construction of New Repository Building
- Provision of new slotted angles racking system for proper storage management.
- Epoxy flooring and wall paint for repository storage area for efficient housing of archives
- UPVC external windows to maximize the efficiency of air conditioning.
- Provision of lift for vertical movement of records.
- Provision of VRF HVAC system that maintains a constant environment for long-term preservation of archive documents.
- Provision of security system like 24/7 digital CCTV coverage, anti-intrusion alarm, enforced controls on access to ensure the safety of the archival documents
Integrated Command & Control Centre under Jammu Smart City Project
Project Cost of ICCC with Data Center, ITMS and eBill Pay for Civic Services (WebGIS): ₹ 143.02Cr.
Integrated Command and Control Center
- ICCC Jammu has been established at 1st Floor, JMC Building.
- ICCC Software Suite has been installed and integration with ITMS, VMS, VMD, PBS, Env. Sensors is completed.
- Integration with Fire and Health Department is under progress.
- 5 Traffic Personnel + 2 Police Personal + 2 helpline operators seated at ICCC.
Heritage Trail & Beautification of Mubarak Mandi to Raghunath Bazar.
- Project Cost: ₹ 16.18 Cr.
- Project Status : Work in progress.
- Physical Progress : 20%
- Date of Start – 30-05-2022; Date of Completion : March - 2024
Project Features
- Road Improvement from Panjthirthi to Raghunath Bazar via Pucca Danga and Jain Bazar.
- Wide walking area.; Traffic management measures.
- Construction of drains and footpaths.
- Improvement of Parks: Rani park and Purani Mandi.
- Cobble stone flooring at Raghunath Bazar, Mubarak Mandi – Panjtirthi and major intersections.
- Construction of Gate at Bharat Mata Chowk.
- Pick-up/ drop-off locations; paid parking.
- Uniform shop signages along Panjtirthi – Mubarak Mandi and Raghunath Bazaar stretches.
- Decorative lighting & realignment of poles; Refurbished / new water points.
- Undergrounding of Communication cables; Cobbled stone intersections (raised) & Sand stones footpaths
Integrated Command & Control Centre under Jammu Smart City Project
Intelligent Traffic Management System
- 44 Traffic Signal Locations
- Live video feed available for 43 Traffic signal location at ICCC Jammu with a storage capacity for 5 days.
- 20 Traffic Signal Locations have been configured for ITMS Analytics (ANPR, RLVD, No Helmet, Triple Riding). Configuration for other analytics such as No Helmet, No Seat Belt, Wrong Lanning / Parking in progress.
- 29 Non-Traffic Signal Locations
- Live video feed available 26 locations at ICCC Jammu with a storage capacity of 5 days.
- E-Challans
- 5 Traffic Personnel seated at ICCC Jammu for issuing E-Challan remotely. Till May End 28,000 Challans worth Rs 3Cr. have been issued.
- City Surveillance
- 2 Police personals have been nominated for ICCC Jammu for surveillance and video feed study in case of investigation.